OFFICE HOURS

Monday - Friday:
8 am - 4:30 pm

1010 Sparkman St NW
Hartselle AL, 35640

(256) 773-3340



Next Board Meeting

Board Meeting
Monday, May 6, 2013
@ 6pm

Board Members
Click here for agenda




ANNOUNCEMENTS

There are no scheduled
outages at this time.

There are no scheduled
outages at this time.

There are no scheduled
outages at this time.



Work In Progress


Natural Gas

Gas System Master Plan

System wide assessment of Gas System

Gas main relocation

Where: Railroad Street
Part of the Longhorn Pass Downtown Bypass Project

Cast iron main replacement

Where: Mynatt/Hill Street(s)
To reinforce system integrity

Bethel Road Construction Update

In early fall, HU crews completed Phase 2 of planned sewer repairs in the Bethel Road area in preparation for the new high school, says HU Engineering Services Manager Glen Partlow. Next, utility crews will relocate water, gas and electric service so that Bethel Road can be widened.
Work to relocate water mains began in December, and is expected to last about 11 weeks, Partlow says. One road closure was expected, and was planned during the winter break to minimize impact on school traffic at F.E. Burleson Elementary School.
Moving the natural gas mains, which will begin in January, will be done by directional boring, where possible, to minimize digging, Partlow reports. “We might go as much as 500 feet with pipe, without disturbing the ground.”
All of HU’s relocations are scheduled to be completed before April, when the City will open the widening and repaving portion of the project up for bids.

2” steel main replacement

Where: Vaughn Bridge Road (Barclift St. to Lakewood St.)
To reinforce system integrity



Electric System

Replacement of bad utility poles

System wide for overall integrity of the electric system

Re-mounting of cross-arm mounted transformers

System wide to reduce outages caused by animals

Electric Crews Replacing Poles

Electric crews inspected all poles in the Northeast section of Hartselle, east of Hwy. 31 and north of Main Street, in November, says Electric Superintendent Jonathan Hampton. Poles with problems that were not treatable will be replaced in the coming months.
In addition, Hampton says, line clearing crews have been working in the Northwest quadrant of the city, west of Hwy. 31 and north of Nance Ford Road. HU crews remove brush and trim trees along power lines in order to minimize power outages caused by trees and limbs falling across the lines.
This work will soon be completed for fiscal year 2013, Hampton says.

Annual testing of commercial/industrial meters

System wide to validate meter reliability



Water

Water System Master Plan

System wide assessment of the Water System

Water Main Relocation

Where: Railroad Street
Part of the Longhorn Pass Downtown Bypass Project

Fire Hydrant Maintenance and Replacement

System wide to maintain adequate fire protection for the City of Hartselle

Bethel Road Construction Update

In early fall, HU crews completed Phase 2 of planned sewer repairs in the Bethel Road area in preparation for the new high school, says HU Engineering Services Manager Glen Partlow. Next, utility crews will relocate water, gas and electric service so that Bethel Road can be widened.
Work to relocate water mains began in December, and is expected to last about 11 weeks, Partlow says. One road closure was expected, and was planned during the winter break to minimize impact on school traffic at F.E. Burleson Elementary School.
Moving the natural gas mains, which will begin in January, will be done by directional boring, where possible, to minimize digging, Partlow reports. “We might go as much as 500 feet with pipe, without disturbing the ground.”
All of HU’s relocations are scheduled to be completed before April, when the City will open the widening and repaving portion of the project up for bids.



Wastewater

Sewer System Rehabilitation

Where: East and Southern Areas
Prevention of sewer overflows, extended system life and treatment plant capacity

Rehabilitation of the East Oxidation Ditch

Location: Wastewater Treatment Plant
To increase the efficiency of the Wastewater Treatment Plant

Bethel Road Construction Update

In early fall, HU crews completed Phase 2 of planned sewer repairs in the Bethel Road area in preparation for the new high school, says HU Engineering Services Manager Glen Partlow. Next, utility crews will relocate water, gas and electric service so that Bethel Road can be widened.
Work to relocate water mains began in December, and is expected to last about 11 weeks, Partlow says. One road closure was expected, and was planned during the winter break to minimize impact on school traffic at F.E. Burleson Elementary School.
Moving the natural gas mains, which will begin in January, will be done by directional boring, where possible, to minimize digging, Partlow reports. “We might go as much as 500 feet with pipe, without disturbing the ground.”
All of HU’s relocations are scheduled to be completed before April, when the City will open the widening and repaving portion of the project up for bids.

Barkley Bridge Sewer and Pumping Station

Where: Garner Road
Provide sewer service to areas south of Nanceford Road and west of Garner Road